Floyd Central High School Project Overview

 
General Comments

-29 classrooms in the two-story addition were turned over during Spring Break.

 -The Administration Area and the Restrooms between the Gyms will be turned over to the Owner on May 1st.

 

 Site Work

 We are continuing work on the West Parking Lot (Old Football Field).  The storm lines have been installed at the West Lot.  We are setting light poles and installing topsoil in front of the new two story addition.  We have started to clean around the new Band/Orchestra Addition.

 

 New 2-story Classroom Addition

 We turned over 29 classrooms during Spring Break.  The owner moved into a few rooms during spring break and the rest the week afterwards.  The remaining 1 classroom, a storage room, and the elevator will be turned over May 1st.

 

 Administration Area

 We are currently painting, installing ceiling grid, and installing woodwork.  We will begin installation of casework and carpet, and continue work in the rotunda.  This area will be turned over on May 1st.

 

 Partial Upper Unit C / Unit A (Band / Orchestra Addition)

 Unit C:  The flooring has been installed in the weight room and cardio room.  We are in the process of getting the elevator inspected for access to the second floor of the Band area.

 

Unit A:  We are continuing brick work.  We have begun drywall finishes, installation of sound doors, and setting of windows.  We will begin painting and ceiling grid work.  The stairs and rails within the orchestra and band rooms have been set and treads are poured.  The lockers and aluminum entrances in the corridor have been installed.

 

 Pool/Pool Storage Rooms

 Pool:  The column repair work has been completed.  We have begun painting.  The pool liner will be installed after the painting, and the flooring will follow.

 Pool Storage Rooms:  These rooms are complete and have been turned over for the Owner’s use.

 

 Commons Area Steel:

 Commons Area Steel:  The ceilings have been removed throughout the main spine of the building during Spring Break, with the exception of the kitchen area.  This allowed us to relocate utilities during Spring Break as well.  We installed the new foundations for some of the new steel columns to be installed this summer.  The entire existing roof (Lower roof) will be removed in the Summer of 2009.

 

 Mechanical Pipe Routes

 The mechanical room work will continue throughout the project.

 

 Restrooms between Gyms:

 We have completed the demolition.  Painting in complete and ceiling grid has been installed.  The plumbing fixtures are being installed.  Ceramic tile will start after the completion of the fixtures.  This area is to be turned over on May 1st.

 

 Partial of Ms. Hampton’s Area:

 The demolition has been completed.  Painting has started.  Ceiling grid work will start after the painting is complete.

 


New Kitchen & Cafeteria:

 

 We have completed the demolition.  We are continuing the underground plumbing and electrical rough-ins.  We have started preparations for pouring the new concrete floor within the new Kitchen area.  Once that is complete we will start metal stud framing and masonry work.

 
New Special Ed Area:

 We installed the temporary wall during Spring Break.  We have begun the interior demolition, as well as the removal of the exterior brick.  The new brick installation has begun.  We will continue rough-ins and demolition as areas are turned over to us.



Orchestra Room


Administration Area Corridor


Main Entrance Rotunda


New Kitchen Area

Click here for printable version of this report.
Email thisEmail | PermalinkPermalink | digg this! share on facebook Stumble Upon Del.icio.us
Archive
Floyd Central High School RSS Subscribe
Add 'Floyd Central High School' to iGoogle
Add 'Floyd Central High School' to My AOL
Add 'Floyd Central High School' to My Yahoo!

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS