Floyd Central High School Project Overview

General Comments
The students and staff are back in the building.  Everything went smooth with them entering back into the building.

Prior to opening the new Art Rooms the Temporary Entrance will have to be relocated.  We reviewed our plan with Mr. Wiseheart and Mr. Jensen.  This relocation work is underway.

Site Work
The loading dock is nearly complete.  The sidewalks in front of the Art Rooms are complete and the fence has been removed.  The seed and straw will be completed in the areas outside the fence.  The fence has been installed at the Bus/Band Parking Lot, temporary parking lot has been installed for Student Parking, and the striping at the temporary/bus parking lot is completed.

New 2-story Classroom Addition
The 2nd floor bearing walls have started and the 1st & 2nd floor slabs have been poured.  Metal stud framing has started and the M/E/P/F Rough-ins will be continuing.  The elevator shaft is completed.

New Art Rooms Addition
The brick and windows are complete.  The painting, ceiling grid, and casework have started.  The M/E/P/F Rough-ins are complete and will begin installing light fixtures.  The Owner Furnished furniture is scheduled for delivery on September 15th.

Partial Upper Unit C/Unit A
Unit C:  The M/E Rough-ins are nearly complete and the painting continues.  Stair #17 will be set.

Unit A:  The foundations and the 1st floor slab are complete.  The structural steel has been delivered and will start being set.  The masonry work is 30% complete and the egress tunnel and temporary walk have been completed.

ROTC/Cross Cut Hallway/Gym Locker Rooms
ROTC:  The painting is around 85% complete.  The acoustical ceilings, ceramic tile, flooring, and the locker installations have started.  The Owner Furnished furniture is scheduled for delivery on September 15th.

Cross Cut Hallway:  The hallway framing is complete, the ceiling and flooring will start as soon as the gym lockers have been installed.

Gym Locker Rooms:  The framing and masonry is completed.  The painting, ceramic tile and the locker installations have started.

Pool/Pool Storage Rooms
The Pool sandblasting is completed.  The M/E/P/F Rough-ins are continuing and the pool equipment will start being installed.

Pool Storage Rooms:  The temporary classroom will be completed.

Commons Area Steel/Commons Restrooms

Commons Area Steel:  The steel is completed. The acoustical deck, foam roof, and metal framing are 70% complete.  The metal clad panels and windows will start in the near future.

Commons Restroom:  The restrooms are open for use.

Mechanical Pipe Routes
The mechanical room work will continue throughout the project.

Floyd sept blog
Band/orchestra addition - exterior walls being installed

Floyd sept blog
Commons area restroom

Floyd Sept blog
Two story addition - 2nd floor (looking west)

Floyd sept blog
Two-story addition - 1st floor (looking west)

Floyd Sept blog
Main entrance at rotunda and art room addition

Floy Sept blog
Loading dock

Click here for printable version.


Posted by Jamie Hergott

Floyd Central High School Project Overview

General Comments
None

Site Work
The curbs have been completed in the front and at the student Parking Lot.  Asphalt base is also complete.  The sidewalks have been poured outside the Construction Areas.  Temporary fence is being relocated and temporary walks for the Main Entrance will be completed prior to July 31st.  Striping of the Parking Lot and Signage will be installed for traffic direction in the near future.  The work at the Loading Dock will begin very soon.

New 2-story Classroom Addition
The 1st Floor masonry bearing walls and the 2nd Floor steel bar joists are completed.  The 2nd Floor decking and the concrete decking will be starting soon.  Setting of steel is nearly complete.

New Art Rooms Addition
The framing and masonry are complete.  The drywall work is continuing.  The mechanical, electrical, fire, and plumbing rough-ins are nearly complete.  Field measurements of the windows and casework are completed.  The temporary entrance through E107 is nearly complete.  The brick work has started.

Partial Upper Unit C/Unit A
Unit C:  The elevator shaft and metal stud framing are completed.  The drywall and mechanical, electrical, fire, and plumbing rough-ins are nearly complete.  Painting is continuing.  The masonry Stair #17 is nearly complete and we will begin setting the steel for Stair #17.

Unit A:  The foundation work continues and the underground plumbing is nearly complete.  The construction of the egress tunnel and temporary sidewalk for student parking will start prior to July 31st.

ROTC/Cross Cut Hallway/Gym Locker Rooms
ROTC:  The mechanical, electrical, fire, and plumbing rough-ins are complete.  Painting is nearly complete.  The acoustical ceiling has started and the flooring and ceramic tile will begin soon.

Cross Cut Hallway is nearly complete.

Gym Locker Rooms:  The mechanical, electrical, fire, and plumbing rough-ins and the masonry are nearly complete.  The metal stud framing has started.

Pool/Pool Storage Rooms
The Pool demolition is complete.  Demolition of Pool Equipment and sandblasting of Pool Tank will begin in the near future (prior to the start of school).  The mechanical, electrical, fire and plumbing rough-ins will continue.

Pool Storage Rooms:  The masonry is completed.  The temporary electrical and data for the temporary classroom is nearly complete.  Painting has started.

Commons Area Steel/Commons Restrooms
The steel detailing is nearly complete.  The acoustical roof deck has been set and the foam roofing and metal stud framing have started.  The masonry and metal stud framing for the restrooms has started.  The foundations have been poured and the steps for the ROTC have started.  The plumbing fixtures have been delivered and the toilet partitions and access panels have been ordered.  Clean-up of the Commons Area will be complete this week.

Mechanical Pipe Routes
The mechanical room work and electrical work are completed, including the new emergency generator.  The HVAC will be back up and running by July 25th and the HVAC piping will continue through the School year for the additions.

Schedule

New 2-Story Classroom Addition January 14, 2008 to March 20, 2009
New Art Rooms Addition March 3, 2008 to August 1, 2008
Main Gym Locker Rooms/Basement (Existing ROTC Location)/New Hallway March 4, 2008 to October 10, 2008
Storage Rooms in Pool Area April 28, 2008 to October 6, 2008
Mechanical/Electrical/Ductwork Routing February 18, 2008 to January 1, 2009

 Click here for printable version.


Archive
Floyd Central High School RSS Subscribe
Add 'Floyd Central High School' to iGoogle
Add 'Floyd Central High School' to My AOL
Add 'Floyd Central High School' to My Yahoo!

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS