Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition of the parking lots and drives is nearly complete. The Site Utilities are being relocated and new storm lines are being installed. Site fence at the new 2-story addition has been removed and re-installed to make room for the new curbs and asphalt base to be installed this summer.
Site demolition of the Tennis Courts behind Galena is complete and the installation of the storm utilities is continuing. The curbs, sidewalks, and asphalt base will follow this summer.
New 2-story Classroom Addition The masonry bearing walls will start in the near future. Structural steel erection is continuing. Underground plumbing is complete.
New Art Rooms Addition The colored concrete slab has been poured. Metal stud framing has begun. Foamed roof is to be installed this week. MEP/FP rough-ins are continuing.
North Half of Commons Area The roof demolition for the new columns is complete. Demo of restrooms by ROTC steps has begun. They will start setting new columns very soon.
North End of the Upper Level in the Auxiliary Gymnasium The mechanical, electrical, and fire protection rough-ins are continuing. The East elevator and the Stair #17 demolition are nearly completed. Masonry is complete at the old racquetball courts. We will begin setting steel and will follow with 2nd floor concrete pour.
New Band/Orchestra Addition The construction of the new building pad is nearly complete. The foundations and underground work will start immediately after the pad is completed.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway Main Gym Locker Room – Demolition is complete. Mechanical, electrical, plumbing, and fire rough-ins are continuing. Masonry walls are continuing.
ROTC – MEP/FP rough-ins are continuing.
Storage Rooms in Pool Area Door frames have been set. Mechanical, Electrical, Plumbing, and Fire Protection rough-ins are continuing. Masonry work is also continuing.
Mechanical/Electrical Pipe Routes Demolition of the old mechanical room is complete. The continuations of the new pipe routes to the additions are on-going. Demo for new electrical closet near Special Education room has started. The electrical power shutdown work to install new transformer should be complete this week.
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 7, 2008 |
| North Half Commons Area |
March 24, 2008 to August 1, 2008 |
| Upper Level of Aux. Gym |
February 18, 2008 to January 3, 2009 |
| Existing Art Rooms |
June 2, 2008 to September 22, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC Location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 2, 2009 |
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition at the new 2-story addition for the Band/Orchestra area is nearly complete except for entrance.
The relocation of the storm utilities at the rear of the school is nearly complete. Site demolition for partial Tennis Courts behind Galena, will complete demolition and install parking lot this summer.
New 2-story Classroom Addition All footings and foundations are nearly complete; masonry bearing walls have been started. Structural steel is being delivered and erection has begun. Underground plumbing is nearly completed. The slab on grade work will start in the near future.
New Art Rooms Addition The installation of underground plumbing and electrical is complete. The foundations are also complete. The structural steel erection is nearly complete. MEP/FP Rough-ins have started. Metal stud framing on Roof has started. The slab on grade work has started this week.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins are continuing. Drywall is currently being installed. Demolition is continuing at the racquetball courts. These areas will become the new wrestling room, weight lifting room, cardio room, and dance room. The East elevator and the SW Stair demolition are nearly completed.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway Main Gym Locker Room – Demolition is complete. Mechanical, electrical, plumbing, and fire rough-ins are continuing. Masonry walls are continuing.
ROTC – Demolition and metal stud framing are complete, drywall is nearly complete. MEP/FP rough-ins are continuing.
Storage Rooms in Pool Area The pool has been drained. The new construction of the Temporary Classrooms in the pool has started. Mechanical, electrical, plumbing, and fire rough-ins have started. Demolition of new door openings has been completed in the Storage Room’s from Hallway.
Construction Dates:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 1, 2009 |
Click here for printable version.
Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition at the new 2-story addition for the Band/Orchestra area has started.
The relocation of the storm utilities at the rear of the school have also started.
New 2-story Classroom Addition The existing concrete slab has been removed. The preparation of the building pad is nearly complete. The main underground storm and water line utilities have been installed across the main entrance of the building. We are continuing with the rest of the underground plumbing and electrical work. We are also continuing with the installation of the foundations.
New Art Rooms Addition The site demolition has been completed. The interior demolition has been completed. The existing structure (building) has been removed. The building pad has been created and approved. The installation of underground plumbing and electrical is nearly complete. The foundations are also nearly complete. The structural steel erection has started.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins are continuing. Drywall is currently being installed. Demolition is continuing at the racquetball courts. These areas will become the new wrestling room, weight lifting room, cardio room, and dance room.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway The demolition is continuing in the locker rooms of the ROTC area. The metal stud walls have been installed. The plumbing and electrical items are being installed into the walls. Door frames have been received and installed in the New ROTC area.
Storage Rooms in Pool Area The pool has been drained. The new construction of the Temporary Classrooms in the pool will start in the near future.
Construction Dates Currently Under Construction:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC location)/ New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 1, 2009 |
 Underground storm sewer at new 2-story addition area
 Demolition of main gym locker rooms
 Exterior foundation wall at the new art room addition
 Metal stud walls and electrical rough-ins at the new ROTC area
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments The appearance of the main entrance will be changing during Spring Break. There will be signs up directing visitors how to enter the building.
New 2-story Classroom Addition The temporary fence has been installed. The existing structure, where the new addition will be placed, has been removed. We are presently removing the concrete slab, in order, to start preparing for the building pad, the installation of the foundations, and the installation of the underground plumbing and electrical.
New Art Rooms Addition The temporary fence has been installed around this area as well. The site demolition has started by removing some obstructions around the existing building. The demolition inside the existing building is nearly complete. The existing building demolition will start in the near future. The main entrance, between these two additions, will be relocated to the South for the removal of the existing canopy during Spring Break.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins have started. Drywall is being installed. This area will become the new wrestling room.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway The ROTC has been relocated to a temporary classroom. Demolition has started in these areas.
Construction Dates Currently Under Construction:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (existing ROTC location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Mechanical/Electrical |
February 18, 2008 to January 1, 2009 |
 Temporary fencing at new 2-story addition area
 Existing structure removed at new 2-story addition area
 Interior demolition nearly complete at new art rooms addition
 Existing structure to be removed at the new art room addition
Click here for printable version.
Posted by Jamie Hergott Floyd Central High School Project Overview
The General Trades Contractor has built the temporary wall dividing the existing building from the addition area. They have relocated lockers and will soon start relocating all the lockers in the common area. They have completed the demolition within the portion of the building that will be removed. They have removed the cage in the Aux. Gym. They will start the demolition of the ROTC area once they are relocated from the basement as well as the Main Gym Locker rooms. The lay down area and fencing is nearly complete. The fencing at the front of the school is also nearly complete. They have also just started the structural demolition. They will relocate the main doors back about 30’-0” to start the demo of the main entrance (tentatively scheduled for Spring Break).
The Drywall Contractor has started the metal stud framing on the 2nd floor of Unit “C”. This area will become the new wrestling area.
The Mechanical Contractor has continued the demolition and capping of lines. They have also started the above ceiling coordination process.
The Fire Sprinkler Contractor has continued the demolition and capping of lines. They have also started the above ceiling coordination process.
The Electrical/Technology Contractor has continued the demolition and terminating the existing electrical lines from the demolition area. They have also started the above ceiling coordination process. They have also nearly completed the temporary data and outlet drops in the temporary rooms. They have connected the power to Verkler’s Trailer.
Work planned to be performed in the next several months:
1. Demoltion of the two-story building in front of school 2. Relocate the front doors back about 30'-0' 3. Relocating site utilities 4. Begin foundations on the two-story addition in front of school 5. Begin dirt work in front of school and at Music Area Unit 'A'
 Temporary wall for structural removal to start
 Framing of new wrestling area on 2nd floor of Unit 'C'
Click here for printable version. Posted by John Kohlmeyer
Floyd Central High School Project Overview
The General Trades Contractor is building temporary partitions for temporary classrooms and will soon be building the temporary wall dividing the existing building from the addition area.
The Mechanical Contractor has been investigating where to cut piping and cap lines.
The Fire Sprinkler Contractor has been investigating where to cut piping and cap lines.
The Electrical/Technology Contractor has been investigating where to cut power feeding the front section of the building in order for demolition to start
Work planned to be performed in the next several months:
1. Install temporary fencing and lay down area 2. Demolition of the two-story building in front of school 3. Relocating site utilities 4. Begin foundations on the two-story addition in front of school and the two-story addition for the new band area.
 Temporary partition at commons area in front of radio and TV rooms
 Temporary partitions at commons area in front of radio and TV rooms