Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work Installing storm lines at new parking area; completed demo; begin installation of base course; install parking lot lights; complete new entrance from Old Vincennes; install curbs and walks at Southwest corner by new ITE Labs; install walks at Band Addition for egress to student parking lot.
New 2-story Classroom Addition Foam roofing is nearly complete; brick veneer continues; begin installation of windows behind brickwork; continue with temporary enclosures; begin drywall and finishes as areas are enclosed; mechanical, electrical, plumbing and fire rough-ins are continuing; will start elevator installation.
New Art Rooms Addition We will move the CAD Teacher to the middle Art Room and work on completing Punch List items.
Partial Upper Unit C/Unit A Unit C: Owner will move in upstairs Gym except for Weight Room. Need to complete masonry in Weight Room and paint. Lights in elevator are complete and restrooms in front of auditorium are complete.
Unit A: Brick veneer on North and South sides are complete, all second floor concrete is complete, masonry is nearly complete, tunnel entrance will be blocked off and egress moved to the North and South until Rotunda Area is complete.
ROTC/Cross Cut Hallway/Gym Locker Rooms ROTC: Owner has moved in and Punch List has been issued.
Cross Cut Hallway: Complete except for flooring and Punch List being issued.
Gym Locker Rooms: Owner has moved in.
Pool/Pool Storage Rooms Pool: Demolition of pool equipment is complete. Began installation of new pool equipment and will continue with mechanical, electrical, plumbing, fire rough-ins. Will start painting Pool Room and begin patching and coating the pool.
Pool Storage Rooms: The floor is installed. Will begin painting, installation of doors and hardware, and installation of temporary doors to pool and open pool hallway.
Commons Area Steel: Commons Area Steel: Metal panels and windows are nearly complete. Will continue with relocation of utilities. Lower roof to be removed in the Summer of 2009.
Mechanical Pipe Routes The mechanical room work will continue throughout the project.
Existing Art Rooms (Industrial Tech): Demolition complete, framing complete, masonry complete, drywall and insulation complete, drywall finishes nearly complete, mechanical, electrical, plumbing, and fire rough-ins nearly complete, painting and acoustical panels will begin.
 New ROTC Area
 New Main Entrance
 Old Football Field
 Steel at the Band/Orchestra Addition
 New Crosscut Corrider
 Classroom Two-Story Addition at the Rotunda
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The installation of the storm line, curb, and sidewalk from Edwardsville-Galena Road up to the existing Football Field is completed. Seeding and straw have been completed outside the fence. We will begin demolition on the existing Football Field and start constructing the Parking Lot after the last Football Game.
New 2-story Classroom Addition All structural steel has been set and steel detailing is nearly completed. Mechanical, electrical, plumbing, and fire protection rough-ins are continuing along with the framing. We will begin foam roofing, continue the brick work, and the elevator has been delivered.
New Art Rooms Addition The punch list has been issued and is being completed. The new furniture has been delivered and installed. The certificate of occupancy was issued and the Owner has occupied the Art Rooms since the beginning of October.
North End of the Upper Level in the Auxiliary Gymnasium Painting has been completed in the Wrestling, Dance, and Cardio Rooms. All of the new lights have been installed. The temporary walls have been removed and the new doors have been installed. Stair #17 has been set and the steps will be poured very soon. The elevator has been delivered and the installation has started. Ceramic tile in Restrooms C147 & C148 has been completed. Plumbing fixtures have been set and installation of the toilet partitions and accessories will begin.
New Band/Orchestra Addition Several of the masonry walls were damaged in the wind storm and have been cleaned up and rebuilt. Masonry is currently 60% complete. Structural Steel components are being set. The 2nd floor slabs have started to be poured. The schedule is approximately 4 weeks behind, due to the wind storm on September 14, 2008.
ROTC/Cross Cut Hallway/Gym Locker Rooms ROTC: Painting, acoustical ceilings, ceramic tile, plumbing fixtures, and lockers are completed. Flooring has started and doors & hardware will be done as the flooring is completed. Stair #20 to the Commons Area is being set and poured. The Owner move in is schedule for this week.
Cross Cut Hallway: Painting and wood trim is completed. Acoustical ceiling is nearly completed. Floor will be leveled and installation of flooring will begin. The Owner will move-in prior to the flooring being completed. The Owner move-in is scheduled for this week.
Gym Locker Rooms: The lockers and acoustical ceilings are completed. The ceramic tile has started and installation of plumbing fixtures, toilet partitions, toilet accessories, and doors and hardware will begin. The Owner move-in is scheduled for this week.
Pool/Pool Storage Rooms Pool: Demolition of the old pool equipment has completed. We have started installing the new pool equipment and will continue with mechanical, electrical, plumbing and fire rough-ins. We will start painting the Pool Room and begin patching and coating the Pool.
Pool Storage Rooms: We will begin final painting this week.
Commons Area Steel/Commons Restrooms Commons Area Steel: The installations of the metal panels and windows have started. We will continue with the foam roofing.
Commons Restroom: The restrooms have been completed and are open for use.
Mechanical Pipe Routes The mechanical room work will continue throughout the project.
Existing Art Rooms (Industrial Tech): The temporary wall has been constructed and demolition is nearly completed. The framing and rough-ins have started. We will begin replacing the exterior brick and a temporary fence has been installed to separate students from workers at this location.
 Art Room
 Started demolition in the Existing Art Rooms
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments The students and staff are back in the building. Everything went smooth with them entering back into the building.
Prior to opening the new Art Rooms the Temporary Entrance will have to be relocated. We reviewed our plan with Mr. Wiseheart and Mr. Jensen. This relocation work is underway.
Site Work The loading dock is nearly complete. The sidewalks in front of the Art Rooms are complete and the fence has been removed. The seed and straw will be completed in the areas outside the fence. The fence has been installed at the Bus/Band Parking Lot, temporary parking lot has been installed for Student Parking, and the striping at the temporary/bus parking lot is completed.
New 2-story Classroom Addition The 2nd floor bearing walls have started and the 1st & 2nd floor slabs have been poured. Metal stud framing has started and the M/E/P/F Rough-ins will be continuing. The elevator shaft is completed.
New Art Rooms Addition The brick and windows are complete. The painting, ceiling grid, and casework have started. The M/E/P/F Rough-ins are complete and will begin installing light fixtures. The Owner Furnished furniture is scheduled for delivery on September 15th.
Partial Upper Unit C/Unit A Unit C: The M/E Rough-ins are nearly complete and the painting continues. Stair #17 will be set.
Unit A: The foundations and the 1st floor slab are complete. The structural steel has been delivered and will start being set. The masonry work is 30% complete and the egress tunnel and temporary walk have been completed.
ROTC/Cross Cut Hallway/Gym Locker Rooms ROTC: The painting is around 85% complete. The acoustical ceilings, ceramic tile, flooring, and the locker installations have started. The Owner Furnished furniture is scheduled for delivery on September 15th.
Cross Cut Hallway: The hallway framing is complete, the ceiling and flooring will start as soon as the gym lockers have been installed.
Gym Locker Rooms: The framing and masonry is completed. The painting, ceramic tile and the locker installations have started.
Pool/Pool Storage Rooms The Pool sandblasting is completed. The M/E/P/F Rough-ins are continuing and the pool equipment will start being installed.
Pool Storage Rooms: The temporary classroom will be completed.
Commons Area Steel/Commons Restrooms
Commons Area Steel: The steel is completed. The acoustical deck, foam roof, and metal framing are 70% complete. The metal clad panels and windows will start in the near future.
Commons Restroom: The restrooms are open for use.
Mechanical Pipe Routes The mechanical room work will continue throughout the project.
 Band/orchestra addition - exterior walls being installed
 Commons area restroom
 Two story addition - 2nd floor (looking west)
 Two-story addition - 1st floor (looking west)
 Main entrance at rotunda and art room addition
 Loading dock
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The curbs have been completed in the front and at the student Parking Lot. Asphalt base is also complete. The sidewalks have been poured outside the Construction Areas. Temporary fence is being relocated and temporary walks for the Main Entrance will be completed prior to July 31st. Striping of the Parking Lot and Signage will be installed for traffic direction in the near future. The work at the Loading Dock will begin very soon.
New 2-story Classroom Addition The 1st Floor masonry bearing walls and the 2nd Floor steel bar joists are completed. The 2nd Floor decking and the concrete decking will be starting soon. Setting of steel is nearly complete.
New Art Rooms Addition The framing and masonry are complete. The drywall work is continuing. The mechanical, electrical, fire, and plumbing rough-ins are nearly complete. Field measurements of the windows and casework are completed. The temporary entrance through E107 is nearly complete. The brick work has started.
Partial Upper Unit C/Unit A Unit C: The elevator shaft and metal stud framing are completed. The drywall and mechanical, electrical, fire, and plumbing rough-ins are nearly complete. Painting is continuing. The masonry Stair #17 is nearly complete and we will begin setting the steel for Stair #17.
Unit A: The foundation work continues and the underground plumbing is nearly complete. The construction of the egress tunnel and temporary sidewalk for student parking will start prior to July 31st.
ROTC/Cross Cut Hallway/Gym Locker Rooms ROTC: The mechanical, electrical, fire, and plumbing rough-ins are complete. Painting is nearly complete. The acoustical ceiling has started and the flooring and ceramic tile will begin soon.
Cross Cut Hallway is nearly complete.
Gym Locker Rooms: The mechanical, electrical, fire, and plumbing rough-ins and the masonry are nearly complete. The metal stud framing has started.
Pool/Pool Storage Rooms The Pool demolition is complete. Demolition of Pool Equipment and sandblasting of Pool Tank will begin in the near future (prior to the start of school). The mechanical, electrical, fire and plumbing rough-ins will continue.
Pool Storage Rooms: The masonry is completed. The temporary electrical and data for the temporary classroom is nearly complete. Painting has started.
Commons Area Steel/Commons Restrooms The steel detailing is nearly complete. The acoustical roof deck has been set and the foam roofing and metal stud framing have started. The masonry and metal stud framing for the restrooms has started. The foundations have been poured and the steps for the ROTC have started. The plumbing fixtures have been delivered and the toilet partitions and access panels have been ordered. Clean-up of the Commons Area will be complete this week.
Mechanical Pipe Routes The mechanical room work and electrical work are completed, including the new emergency generator. The HVAC will be back up and running by July 25th and the HVAC piping will continue through the School year for the additions.
Schedule
| New 2-Story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC Location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 1, 2009 |
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition of the parking lots and drives is nearly complete. The Site Utilities are being relocated and new storm lines are being installed. Site fence at the new 2-story addition has been removed and re-installed to make room for the new curbs and asphalt base to be installed this summer.
Site demolition of the Tennis Courts behind Galena is complete and the installation of the storm utilities is continuing. The curbs, sidewalks, and asphalt base will follow this summer.
New 2-story Classroom Addition The masonry bearing walls will start in the near future. Structural steel erection is continuing. Underground plumbing is complete.
New Art Rooms Addition The colored concrete slab has been poured. Metal stud framing has begun. Foamed roof is to be installed this week. MEP/FP rough-ins are continuing.
North Half of Commons Area The roof demolition for the new columns is complete. Demo of restrooms by ROTC steps has begun. They will start setting new columns very soon.
North End of the Upper Level in the Auxiliary Gymnasium The mechanical, electrical, and fire protection rough-ins are continuing. The East elevator and the Stair #17 demolition are nearly completed. Masonry is complete at the old racquetball courts. We will begin setting steel and will follow with 2nd floor concrete pour.
New Band/Orchestra Addition The construction of the new building pad is nearly complete. The foundations and underground work will start immediately after the pad is completed.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway Main Gym Locker Room – Demolition is complete. Mechanical, electrical, plumbing, and fire rough-ins are continuing. Masonry walls are continuing.
ROTC – MEP/FP rough-ins are continuing.
Storage Rooms in Pool Area Door frames have been set. Mechanical, Electrical, Plumbing, and Fire Protection rough-ins are continuing. Masonry work is also continuing.
Mechanical/Electrical Pipe Routes Demolition of the old mechanical room is complete. The continuations of the new pipe routes to the additions are on-going. Demo for new electrical closet near Special Education room has started. The electrical power shutdown work to install new transformer should be complete this week.
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 7, 2008 |
| North Half Commons Area |
March 24, 2008 to August 1, 2008 |
| Upper Level of Aux. Gym |
February 18, 2008 to January 3, 2009 |
| Existing Art Rooms |
June 2, 2008 to September 22, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC Location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 2, 2009 |
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition at the new 2-story addition for the Band/Orchestra area is nearly complete except for entrance.
The relocation of the storm utilities at the rear of the school is nearly complete. Site demolition for partial Tennis Courts behind Galena, will complete demolition and install parking lot this summer.
New 2-story Classroom Addition All footings and foundations are nearly complete; masonry bearing walls have been started. Structural steel is being delivered and erection has begun. Underground plumbing is nearly completed. The slab on grade work will start in the near future.
New Art Rooms Addition The installation of underground plumbing and electrical is complete. The foundations are also complete. The structural steel erection is nearly complete. MEP/FP Rough-ins have started. Metal stud framing on Roof has started. The slab on grade work has started this week.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins are continuing. Drywall is currently being installed. Demolition is continuing at the racquetball courts. These areas will become the new wrestling room, weight lifting room, cardio room, and dance room. The East elevator and the SW Stair demolition are nearly completed.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway Main Gym Locker Room – Demolition is complete. Mechanical, electrical, plumbing, and fire rough-ins are continuing. Masonry walls are continuing.
ROTC – Demolition and metal stud framing are complete, drywall is nearly complete. MEP/FP rough-ins are continuing.
Storage Rooms in Pool Area The pool has been drained. The new construction of the Temporary Classrooms in the pool has started. Mechanical, electrical, plumbing, and fire rough-ins have started. Demolition of new door openings has been completed in the Storage Room’s from Hallway.
Construction Dates:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 1, 2009 |
Click here for printable version.
Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments None
Site Work The site demolition at the new 2-story addition for the Band/Orchestra area has started.
The relocation of the storm utilities at the rear of the school have also started.
New 2-story Classroom Addition The existing concrete slab has been removed. The preparation of the building pad is nearly complete. The main underground storm and water line utilities have been installed across the main entrance of the building. We are continuing with the rest of the underground plumbing and electrical work. We are also continuing with the installation of the foundations.
New Art Rooms Addition The site demolition has been completed. The interior demolition has been completed. The existing structure (building) has been removed. The building pad has been created and approved. The installation of underground plumbing and electrical is nearly complete. The foundations are also nearly complete. The structural steel erection has started.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins are continuing. Drywall is currently being installed. Demolition is continuing at the racquetball courts. These areas will become the new wrestling room, weight lifting room, cardio room, and dance room.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway The demolition is continuing in the locker rooms of the ROTC area. The metal stud walls have been installed. The plumbing and electrical items are being installed into the walls. Door frames have been received and installed in the New ROTC area.
Storage Rooms in Pool Area The pool has been drained. The new construction of the Temporary Classrooms in the pool will start in the near future.
Construction Dates Currently Under Construction:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC location)/ New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 1, 2009 |
 Underground storm sewer at new 2-story addition area
 Demolition of main gym locker rooms
 Exterior foundation wall at the new art room addition
 Metal stud walls and electrical rough-ins at the new ROTC area
Click here for printable version. Posted by Jamie Hergott
Floyd Central High School Project Overview
General Comments The appearance of the main entrance will be changing during Spring Break. There will be signs up directing visitors how to enter the building.
New 2-story Classroom Addition The temporary fence has been installed. The existing structure, where the new addition will be placed, has been removed. We are presently removing the concrete slab, in order, to start preparing for the building pad, the installation of the foundations, and the installation of the underground plumbing and electrical.
New Art Rooms Addition The temporary fence has been installed around this area as well. The site demolition has started by removing some obstructions around the existing building. The demolition inside the existing building is nearly complete. The existing building demolition will start in the near future. The main entrance, between these two additions, will be relocated to the South for the removal of the existing canopy during Spring Break.
North End of the Upper Level in the Auxiliary Gymnasium The walls have been erected along with the new door and window frames. The mechanical, electrical, and fire protection rough-ins have started. Drywall is being installed. This area will become the new wrestling room.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway The ROTC has been relocated to a temporary classroom. Demolition has started in these areas.
Construction Dates Currently Under Construction:
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 1, 2008 |
| Main Gym Locker Rooms/Basement (existing ROTC location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Mechanical/Electrical |
February 18, 2008 to January 1, 2009 |
 Temporary fencing at new 2-story addition area
 Existing structure removed at new 2-story addition area
 Interior demolition nearly complete at new art rooms addition
 Existing structure to be removed at the new art room addition
Click here for printable version.
Posted by Jamie Hergott Floyd Central High School Project Overview
The General Trades Contractor has built the temporary wall dividing the existing building from the addition area. They have relocated lockers and will soon start relocating all the lockers in the common area. They have completed the demolition within the portion of the building that will be removed. They have removed the cage in the Aux. Gym. They will start the demolition of the ROTC area once they are relocated from the basement as well as the Main Gym Locker rooms. The lay down area and fencing is nearly complete. The fencing at the front of the school is also nearly complete. They have also just started the structural demolition. They will relocate the main doors back about 30’-0” to start the demo of the main entrance (tentatively scheduled for Spring Break).
The Drywall Contractor has started the metal stud framing on the 2nd floor of Unit “C”. This area will become the new wrestling area.
The Mechanical Contractor has continued the demolition and capping of lines. They have also started the above ceiling coordination process.
The Fire Sprinkler Contractor has continued the demolition and capping of lines. They have also started the above ceiling coordination process.
The Electrical/Technology Contractor has continued the demolition and terminating the existing electrical lines from the demolition area. They have also started the above ceiling coordination process. They have also nearly completed the temporary data and outlet drops in the temporary rooms. They have connected the power to Verkler’s Trailer.
Work planned to be performed in the next several months:
1. Demoltion of the two-story building in front of school 2. Relocate the front doors back about 30'-0' 3. Relocating site utilities 4. Begin foundations on the two-story addition in front of school 5. Begin dirt work in front of school and at Music Area Unit 'A'
 Temporary wall for structural removal to start
 Framing of new wrestling area on 2nd floor of Unit 'C'
Click here for printable version. Posted by John Kohlmeyer
Floyd Central High School Project Overview
The General Trades Contractor is building temporary partitions for temporary classrooms and will soon be building the temporary wall dividing the existing building from the addition area.
The Mechanical Contractor has been investigating where to cut piping and cap lines.
The Fire Sprinkler Contractor has been investigating where to cut piping and cap lines.
The Electrical/Technology Contractor has been investigating where to cut power feeding the front section of the building in order for demolition to start
Work planned to be performed in the next several months:
1. Install temporary fencing and lay down area 2. Demolition of the two-story building in front of school 3. Relocating site utilities 4. Begin foundations on the two-story addition in front of school and the two-story addition for the new band area.
 Temporary partition at commons area in front of radio and TV rooms
 Temporary partitions at commons area in front of radio and TV rooms
Click here for printable version.
|